1Coming in
← Buying
Purchase order · merchant, Northallerton

PO-3104

Received

To Northern Clay Distribution, Andrea Blake. 1 line, 87 packs, £26,604.60 ex VAT at cost, 30 days EOM terms.

Received
Booked in Fri 18 Sep

Checked in against the PO, no differences.

87packs
£26,605at cost
18 Sepbooked in
  1. Raised
    Fri 11 Sep 09:10
    by Sophie
  2. Sent
    Fri 11 Sep
    to Andrea Blake
  3. Confirmed
    Done
    by Northern Clay Distribution
  4. On the road
    Done
    Delivered
  5. Landed
    Fri 18 Sep
    At Aire Works
  6. Booked in
    Fri 18 Sep 09:46
    by Gary, against the PO
What came in
Every line counted off the lorry against the PO by Gary, then forked into its bay.
ProductReceivedCostValueOn hand now
Engineering brick, red, 75mm, pack of 424
Pack of 424 bricks NEB-R75-424
87 packs£305.80£26,604.607,632 bricks
Supplier
Northern Clay Distribution
New engineering bricks: 75mm red engineering brick
Open →
Lead time5 days
On time, last 12 months88%
Terms30 days EOM
Minimum order£2,000
This order is £26,605, over the £2,000 minimum.
PO-3114 on the road, with us Fri 13 Nov; the 75mm red engineering brick is short until then
History
  1. Raised by Sophie
    Fri 11 Sep 09:10 · Sophie
  2. Booked in by Gary: Checked in against the PO, no differences.
    Fri 18 Sep 09:46 · Gary